FORM B
REPUBLIC OF MAURITIUS
(MAURITIUS PORTS AUTHORITY)
(Procurement to be undertaken through Open Advertised Bidding)
S/N |
Type/Nature of Procurement |
Procurement Details |
Expected Date of launching of Bid |
---|---|---|---|
|
Services |
Document Management System (DMS) |
September 2025 |
|
Services |
Implementation and Operation of a Vessel Clearance System for Port Louis Harbour on an OPEX Model (Phase 2) |
August 2025 |
|
Services |
Supply, Installation, Configuration, Training, Commissioning and Maintenance of Network Equipment |
August 2025 |
|
Services |
CCTV System at Port Mathurin, Rodrigues |
August 2025 |
|
Services |
Upgrading of Payroll and Migration |
January 2026 |
|
Goods |
Procurement of 4 Small Tugs |
February 2026 |
|
Goods |
Supply, Delivery, Testing and Commissioning Two (2) Trailer-Mounted Fire Pumps |
August 2025 |
|
Works |
Upgrading of Roofsheeting at Shed A |
October 2025 |
|
Works |
Upgrading of Roof to Open Shed at Trou Fanfaron Fishing Port |
August 2025 |
|
Works |
Provision of Jersey Barriers to Oil Pipelines at Mer Rouge |
September 2025 |
|
Works |
Repairs to Revetment at Corney Quay 4 |
August 2025 |
|
Works |
Upgrading of Precast Cover Slabs to Service Tunnel at Terminal 1 |
September 2025 |
|
Services |
Procurement of Fenders for Terminal I & II |
September 2025 |
|
Works |
Upgrading of drain covers at Terminal II |
September 2025 |
|
Services |
Consultancy Services for Replacement of Centralised Airconditioning system at Capitainerie Building |
August 2025 |
|
Services |
Consultancy Services for Upgrading of HT electrical sub station No. 1 at MCT |
November 2025 |
|
Services |
Consultancy Services for Scaling up of Renewable Energy at Port Louis Cruise Terminal with solar PV covered parking |
January 2026 |
Last Updated: 28/07/2025 |
|
Date: July 2025
Note: The information given is for planning purposes and is subject to revision or cancellation. It does not constitute a final commitment to buy the goods and services until the procurement process is initiated.